Week 28 December 5 - December 11:
Week 27 November 28 - December 4:
Week 24 November 14 - November 20:
Week 22 October 31 - November 6:
Week 21 October 24 - October 30: Assembly hall ceiling tiles are now all installed. Some will be removed when lighting is placed in the ceiling. The mixture of used and new tiles looks like we designed it that way! The refinishing of the kitchen floor started on Tuesday and will be complete on Friday with the 2nd coat of polyurethane. What a contrast between the un-refinished floor and the newly done floor in the kitchen! Volunteers came aplenty early in the week to caulk, prime, scrape, and paint. Rosalie and James P., Bruce P., Jeanne D., Jim, David T., Al W., Richard D., Will R. Much accomplished - thanks to all.
Week 5 July 4 - July 10: Preparation work begins. The existing walls are not 'true' so the framer tries several starting points for marking off the framing outline for the walls; rough framing begins.